Confidential Chip Manufacturer Industrial Waste System Expansion
Scope of Work
- Cyanide waste system expansion: installing two new 6425 gallon waste tanks and tying them into the existing waste system
- Provide and install VFDs, motor starters, and new PLCs
Achievements
- champion INNOVATION | integrated project delivery environment
- build TRUST | shared savings resulted from completing project below targeted budgets
Challenges
- operate with EXCELLENCE | coordination with five different trade contractors and one A/E firm
- build TRUST | target costs generated per component of the project with percent of profit at risk
- Owner
- Confidential Chip Manufacturer
- General Contractor
- Turner Construction
- Delivery Method
- Integrated Project Delivery
- Location
- Chandler, Arizona
- Markets
- Industrial & Manufacturing
- Services
- Virtual Construction
- Fabrication
- Electrical Construction
- Completion Date
- January 2016