Confidential Medical Device Manufacturer

Scope of Work

  • Temp power: 4 skids; temp lighting for full building
  • 148,000 SF warehouse building: full build-out of 3/4 building including power, lighting, fire alarm, conduit for security & communication; phased construction; clean room
  • Underground utilities
  • 5 kW generator; 4,000 amp ATS; 4,000 amp SES
  • UPS system – 1 500 KVA, 1 300 KVA, 2 80 KVA; 2 lighting inverters; 50 panels; AHUs

Top Achievements

  • build TRUST | fast track schedule: completing the project in the compressed project schedule – owner added scope without increasing the schedule; we maintained completion date through strong communication, pre-planning, and the use of prefab
  • operate with EXCELLENCE | full team coordination: pre-construction, marketing, estimating, modeling/detailing, prefab, construction, purchasing, safety, tools, accounting, human resources/talent acquisition, labels…….EVERYONE!

Challenges & Solutions

  • champion INNOVATION | overcame design challenges, and equipment lead times; we provided solutions to maintain the schedule by leveraging in-house BIM and fabrication capabilities
  • operate with EXCELLENCE | roof weight capacity: we originally planned to install our feeder conduits overhead but it became apparent that the roof could not hold the weight – the team quickly adjusted to an underground route