Confidential Medical Device Manufacturer
Scope of Work
- Temp power: 4 skids; temp lighting for full building
- 148,000 SF warehouse building: full build-out of 3/4 building including power, lighting, fire alarm, conduit for security & communication; phased construction; clean room
- Underground utilities
- 5 kW generator; 4,000 amp ATS; 4,000 amp SES
- UPS system – 1 500 KVA, 1 300 KVA, 2 80 KVA; 2 lighting inverters; 50 panels; AHUs
Top Achievements
- build TRUST | fast track schedule: completing the project in the compressed project schedule – owner added scope without increasing the schedule; we maintained completion date through strong communication, pre-planning, and the use of prefab
- operate with EXCELLENCE | full team coordination: pre-construction, marketing, estimating, modeling/detailing, prefab, construction, purchasing, safety, tools, accounting, human resources/talent acquisition, labels…….EVERYONE!
Challenges & Solutions
- champion INNOVATION | overcame design challenges, and equipment lead times; we provided solutions to maintain the schedule by leveraging in-house BIM and fabrication capabilities
- operate with EXCELLENCE | roof weight capacity: we originally planned to install our feeder conduits overhead but it became apparent that the roof could not hold the weight – the team quickly adjusted to an underground route
- Owner
- Confidential
- General Contractor
- Skanska
- Location
- Mesa, AZ
- Markets
- Industrial, Manufacturing
- Services
- Virtual Construction
- Fabrication
- Electrical Construction
- Electrical Service
- Completion Date
- July 2017