FAA Cooling Tower Modernization

Scope of Work

  • Replace cooling towers and associated pumps, VFDs, and electrical systems
  • LED lighting upgrades in host computer and communications equipment rooms

Achievements

  • build TRUST | LED lighting upgrade completed in occupied area of building with no impacts to operations or facility personnel
  • build TRUST | panel upgrades and relocations completed in a critical/operating FAA facility with no impacts to operations
  • operate with EXCELLENCE | pre-planning and having correct materials were key to keeping productivity high

Challenges

  • build TRUST | coordination on multiple electrical shut-downs of panels and MCCs
  • operate with EXCELLENCE | multiple site condition impacts not reflected in scope documents, we were able to adjust with minimal impacts
Owner
DOT - Federal Aviation Administration
General Contractor
E-Corp
Location
Albuquerque, New Mexico
Markets
Aviation & Transportation
Services
Electrical Construction
Completion Date
October 2016