Grand Canyon National Park Airport
Scope of Work
- Rehabilitation of airfield lighting system
- New underground duct, cable, isolation transformers, new lighting, signs, new regulators, upgraded LED apron lighting, new hand holes
Project Achievements
- champion INNOVATION | utilization of Bluebeam, resulting in a paperless project, no prints in the field – everything via iPad, including specs, drawings, etc.
Project Challenges
- build TRUST | lost concrete supplier resulting in two week delay / found new local supplier and switched work schedules to complete project ahead of schedule
- build TRUST | remote location so pre-planning and constant communication were crucial
- operate with EXCELLENCE | project began in winter with more than 6″ of snow on ground
- Owner
- Arizona Department of Transportation
- General Contractor
- Fann Contracting
- Location
- Grand Canyon Village, Arizona
- Markets
- Aviation & Transportation
- Services
- Fabrication
- Electrical Construction
- Completion Date
- August 2016